INSP-Sprinkler Rough-in | 7/21/2020 | 7/21/2020 | 7/21/2020 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for garage sprinkler piping complete. Piping can be painted before rough in inspection requests.
Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
Issue and Print Permit | | | 12/30/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/18/2019 | | 12/24/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/24/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 12/24/2019 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 12/18/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/4/2019 | | 9/19/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 9/4/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 9/4/2019 | | 9/4/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 9/3/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 3 2019 9:37AM
|