INSP-Final Inspection | 6/5/2020 | 6/11/2020 | 6/12/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Phone #: ###-#### Inspection requested via web by Michelle Cooper
|
INSP-Final Inspection | 5/18/2020 | 5/21/2020 | 5/21/2020 | A | FAIL |
Troy Cobbley
|
|
|
Provide a one hour rated riser room, provide heat for the riser room as discussed, provide ball drip for the FDC, provide forward flush testing, provide walk through to verify final sprinkler head placement. All interconnections with the FACP tested ok. Inspection requested via web by Connie Danes
|
Telephone call | | | 5/21/2020 | | DONE |
Joe Bruce
|
|
|
Given the size of the small size (<600 SF) of the building and that this is a non-required fire sprinkler system, acceptable to omit the 1-hour fire rating requirement per conversation with assistant Fire Marshal. I also spoke with Tim (General Contractor) and the exterior door for this fire riser room is insulated and the temperature of the past winter allows enough residual heat in this room to keep it above 40 degrees. Owner required to keep temperature in this room above 40F. **JHB**
|
INSP-Final Inspection | 4/9/2020 | 4/14/2020 | 4/14/2020 | A | FAIL |
Jim Page
|
|
|
Fire sprinkler system is required to be supervised per the 2015 IFC, section 903.4.
Josh Danes Cell Number: ###-#### Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 1/30/2020 | 1/30/2020 | 1/30/2020 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected.
Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 1/23/2020 | 1/24/2020 | 1/24/2020 | P | FAIL |
Troy Cobbley
|
|
|
Need city approved plans that match the layout of the installed piping. Need through bolts for the earthquake attachments at the roof structure.
Rough in for Cover - Jim will attend Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 1/22/2020 | 1/23/2020 | 1/24/2020 | P | CANC |
Troy Cobbley
|
|
|
Cover Inspection, Jim will attend Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in/Hydro | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PASS |
Troy Cobbley
|
|
|
Overhead Hydro test witnessed with no pressure loss.
, Barry will attend. Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 12/10/2019 | 12/12/2019 | 12/12/2019 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Barry Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Supply line flush | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | PASS |
Troy Cobbley
|
|
|
Underground flush witnessed.
Barry Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in/Hydro | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test witnessed.
Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 11/26/2019 | 11/27/2019 | 11/27/2019 | A | PASS |
Troy Cobbley
|
|
|
The underground tie-in piping is ok for cover. Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 11/11/2019 | 11/12/2019 | 11/12/2019 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok for cover.
Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in | 11/7/2019 | 11/8/2019 | 11/8/2019 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Inspection requested via web by Connie Danes
|
Issue and Print Permit | | | 9/16/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/6/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/6/2019 | | 9/6/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 9/6/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 9/5/2019 | | 9/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/5/2019 | | 9/5/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Application received | | | 9/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 4 2019 2:29PM
|