INSP-Final Inspection | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler riser monitoring verified, final fire alarm inspection complete,
Buck Phone #: ###-####
|
INSP-Final Inspection | 10/10/2019 | 10/14/2019 | 10/14/2019 | P | PART |
Jim Page
|
|
|
Tested flow switch, pull, smoke, cell communicator and battery trouble. All worked properly. Sprinkler contractor was not present and sprinkler valve was shut so actual flow and tampers were not functionally tested. Once tested, this permit can be finaled. Phone #: ###-#### >> Inspection requested via web by Ken Webster
|
Plan assigned to (Lee) | 9/5/2019 | | 9/5/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 9/5/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 9/5/2019 | | 9/5/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 9/5/2019 | | DONE |
|
|
|
Passed with review comments.
|
Permit Ready to Issue | | | 9/5/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/5/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/5/2019 | | DONE |
|
|
|
|
Application received | | | 9/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 4 2019 4:20PM
|