INSP-Final Inspection | 10/31/2019 | 11/1/2019 | 11/1/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Jon is the contact in the field. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PART |
Troy Cobbley
|
|
|
The piping above the hardlids is ok to cover. I noted two heads blocked by beams
Richard Clark is the contact for this RTC inspection. We appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/4/2019 | 10/7/2019 | 10/7/2019 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans on site. I noted that two heads along the south wall appear to be blocked by two wood beams. Richard Clark is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Application received | | | 9/5/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 5 2019 7:04AM
|
Intake Approval | | | 9/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 9/5/2019 | | 9/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/5/2019 | | 9/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 9/5/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 9/5/2019 | | DONE |
|
|
|
|