INSP-Final Inspection | 12/10/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final fire sprinkler inspection is complete.
BRYAN Phone #: ###-####
|
Fees Due Hold | 12/6/2019 | | 12/10/2019 | | DONE |
|
|
|
|
INSP-Final Inspection | 12/4/2019 | 12/5/2019 | 12/5/2019 | A | FAIL |
Jim Page
|
|
|
Upright heads throughout space are painted, painted heads are not acceptable per NFPA13.
Damian Phone #: ###-####
|
INSP-Final Inspection | 12/3/2019 | 12/4/2019 | 12/4/2019 | A | FAIL |
Troy Cobbley
|
|
|
***Escutcheons painted in sounds rooms. Heads to close to sound baffles in sound rooms. MAS**
Damien Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 10/4/2019 | | DONE |
|
|
|
|
Plan assigned to (Stumbaugh) | 9/25/2019 | | 9/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/26/2019 | | 9/26/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
Plan Mod Fee $150.00
|
Permit Ready to Issue | | | 9/26/2019 | | |
|
|
|
plan mod approved
|
Plan Modification Accepted | | | 9/25/2019 | | DONE |
|
|
|
as built
|
INSP-Sprinkler Rough-in | 9/13/2019 | 9/16/2019 | 9/16/2019 | P | CANC |
Jim Page
|
|
|
**Inspection done on 9/16/2019*MAS**
Todd Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/16/2019 | 9/16/2019 | 9/16/2019 | P | PASS |
Jim Page
|
|
|
**Passed Above Ceiling. As built drawings needed before final inspection*MAS**
Todd Phone #: ###-####
|
Plan resubmittals received | | | 9/11/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/11/2019 | | 9/11/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 9/11/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/11/2019 | | 9/11/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/11/2019 | | DONE |
Mark Stumbaugh
|
|
|
Add resubmittal fee $110.25
|
Permit Ready to Issue | | | 9/11/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 9/11/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/6/2019 | | 9/10/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Application received | | | 9/6/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 6 2019 9:39AM
|
Intake Approval | | | 9/6/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 9/6/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 9/6/2019 | | 9/6/2019 | | DONE |
Mark Stumbaugh
|
|
|
|