INSP-Supply line flush | 5/29/2020 | 6/2/2020 | 6/2/2020 | A | PASS |
Troy Cobbley
|
|
|
10am flushes on all three undergrounds witnessed. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | PASS |
Troy Cobbley
|
|
|
Underground rough/hydro at Building 10 witnessed with no pressure loss. Piping can be covered. , please call james before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Troy Cobbley
|
|
|
The three cpvc underground supplies for the building that sits along Maple Grove was witnessed.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2019 | 9/27/2019 | 9/27/2019 | P | PART |
Troy Cobbley
|
|
|
Main water supply hydro test witnessed with no pressure loss. The three cpvc supplies all failed due to visible loss at the guages.
Call James, might be ready this morning if you can go out earlier. Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/23/2019 | 9/24/2019 | 9/24/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground rough for the south most building passed and piping can be covered. The hydro on fire line and tower underground feed witnessed. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/22/2019 | 9/23/2019 | 9/23/2019 | P | FAIL |
Troy Cobbley
|
|
|
Underground hydro test failed due to visible loss on the guage.
Underground rough/hydro for supply line and for tower underground connection. Call James before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Issue and Print Permit | | | 9/18/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/10/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 9/10/2019 | | 9/10/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/10/2019 | | 9/10/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 9/10/2019 | | DONE |
|
|
|
|
Application received | | | 9/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 9 2019 8:48AM
|