INSP-Final Inspection | 2/6/2020 | 2/7/2020 | 2/7/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler ispection for scope of work complete.
MIKE OSWALD Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
INSP-Sprinkler Rough-in | 1/20/2020 | 1/21/2020 | 1/21/2020 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 4 complete, 2 heads are less than 4 inches off of wall/corner of wall, a minimum of 4 inches is required. Will verfiy relocate during final inspection. Cover is approved.
Mike Oswald-4th floor please Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
INSP-Sprinkler Rough-in | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for remaining level 5 overhead fire sprinkler piping complete, level 5 approved for cover.
Mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/7/2020 | 1/7/2020 | 1/7/2020 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping east of column line 5 complete, area inspected is notated on city approved drawings with red ink, approved for cover east of column line 5.
MIKE OSWALD Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
INSP-Sprinkler Rough-in | 11/19/2019 | 11/19/2019 | 11/19/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids in scope of work complete, hardlids approved for cover.
Mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/10/2019 | 10/10/2019 | 10/10/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in hardlid dome area complete, area inspected approved for cover, remaining areas to be inspected at a later date.
rough to cover // Mike Phone #: ###-####
|
Sprinkler Plan Check | 9/17/2019 | | 9/19/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 9/19/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/19/2019 | | |
|
|
|
|
Intake Approval | | | 9/17/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 9/17/2019 | | 9/17/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 9/16/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 16 2019 3:27PM
|