INSP-Final Inspection | 11/27/2019 | 11/27/2019 | 11/27/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work is complete, all escutcheon in place at time of inspection.
|
INSP-Sprinkler Rough-in/Hydro | 11/26/2019 | 11/27/2019 | 11/27/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining areas of work complete, approved for cover.
Cooridinated for 0815 per conversation with point of contact, Approved plans are on site, please contact Chris Felty before heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Sprinkler Rough-in | 11/25/2019 | 11/26/2019 | 11/26/2019 | A | CANC |
Jim Page
|
|
|
Rescheduled for 27NOV2019 per conversation with point of contact as well as scheduling issues, this request is cancelled.
Approved plans are on site, please contact Chris Felty before heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Sprinkler Rough-in | 10/1/2019 | 10/2/2019 | 10/2/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in Area 1 of work complete, city approved plans have been notated that area 1 is approved for cover.
Plans have been left on site but please contact Chris Felty prior to heading to job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
Issue and Print Permit | | | 9/27/2019 | | DONE |
|
|
|
|
Application received | | | 9/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 24 2019 7:40AM
|
Intake Approval | | | 9/24/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 9/24/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 9/24/2019 | | 9/24/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/24/2019 | | 9/24/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 9/24/2019 | | DONE |
|
|
|
met
|