INSP-Final Inspection | 11/19/2019 | 11/19/2019 | 11/19/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
|
INSP-Sprinkler Rough-in | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover, flex drops were used in original install, flex drops are in place.
Please Call Rick Fouts 1 hour prior to heading to the job site at Phone #: ###-#### Inspection requested via web by Matt Barnard
|
INSP-Final Inspection | 11/15/2019 | 11/18/2019 | 11/18/2019 | A | CANC |
Troy Cobbley
|
|
|
Tried calling contact phone number twice but automated message said non-working number. Also a rough-in inspection has not been scheduled prior to this scheduled final inspection.
Glen Phone #: ###-####
|
INSP-Final Inspection | 11/14/2019 | 11/15/2019 | 11/15/2019 | A | FAIL |
Jim Page
|
|
|
Called point of contact listed, no answer, left a message. Could not get access to area, could not locate city approved drawings, no rough in inspection requested.
call ahead //Rick Phone #: ###-####
|
Plan Modification Accepted | | | 11/8/2019 | | DONE |
|
|
|
Matt from Delta Fire requested a plan mod workflow
|
Plan assigned to (Stumbaugh) | 11/8/2019 | | 11/8/2019 | | DONE |
Mark Stumbaugh
|
|
|
plan mod
|
Sprinkler Plan Check | 11/8/2019 | | 11/8/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2019 | | DONE |
Mark Stumbaugh
|
|
|
No Fee
|
Permit Ready to Issue | | | 11/8/2019 | | DONE |
|
|
|
plan mod approved- no fe per MAS
|
CHANGE STATUS TO (ISS) | | | 11/8/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/29/2019 | | DONE |
|
|
|
|
Application received | | | 10/28/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 28 2019 12:02PM
|
Intake Approval | | | 10/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 10/28/2019 | | 10/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 10/28/2019 | | 10/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 10/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 10/28/2019 | | DONE |
|
|
|
met
|