INSP-Final Inspection | 12/18/2019 | 12/19/2019 | 12/19/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
Intake Approval | | | 10/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 10/29/2019 | | 10/29/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 10/29/2019 | | 10/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 10/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/29/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 10/29/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 10/29/2019 | | DONE |
|
|
|
|
Application received | | | 10/28/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 28 2019 5:04PM
|