INSP-Final Inspection | 2/13/2020 | 2/18/2020 | 2/18/2020 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | PASS |
Troy Cobbley
|
|
|
Phase 2 sprinkler rough-in passed. Piping can be covered. See plans for two pendants circled in red that have not been installed yet.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
Intake Approval | | | 11/4/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 11/4/2019 | | 11/4/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 11/4/2019 | | 11/4/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 11/4/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/4/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 11/4/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 11/4/2019 | | DONE |
|
|
|
|
Application received | | | 10/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 30 2019 12:14PM
|