Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberFIR19-00888
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 9605 S EISENMAN RD
Project NameBOISE GATEWAY INDUSTRIAL PARK
Customer Number 
ePlanReviewYes
Description
**QUICK PERMIT** UDG Only. SHILO WILL INSTALL APPROXIMATELY 105' OF 8" C900 TO AN 8" STAINLESS STEEL IN-BUILDING RISER. THIS WILL EVENTUALLY FEED A 1500 GPM FIREPUMP AND 5 ESFR SYSTEMS IN A 168,000 FT² NONCOMBUSTIBLE BUILDING.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/18/20206/19/20206/19/2020PPASS
DetailsJim Page
Final inspection for underground supply complete.

Jeff Chaney is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/18/20206/19/20206/19/2020AFAIL
DetailsJim Page
Wrong permit requested for type of inspection.

This is a Fire Pump Final. Contact is Jeff Chaney Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection6/18/20206/19/20206/18/2020ACANC
DetailsJim Page
The contact is Jeff Chaney. Have a good day!! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro6/17/20206/18/20206/18/2020APASS
DetailsTroy Cobbley
The overhead hydro for the five systems was witnessed with no pressure loss. Header, FDC and fire pump piping was not tested.


Jeff Chaney is the contact. Thanks so much! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro6/17/20206/17/20206/17/2020PDONE
DetailsJim Page
Hydrostatic test for underground supply witnessed via photo, no pressure loss observed by timed photos.

Jeff Chaney is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush6/16/20206/17/20206/17/2020ADONE
DetailsJim Page
Main line underground flush complete.

Jeff Chaney is the contact. Thanks so much! Phone #: ###-#### Inspection requested via web by Stan Beus, coordinated for 0830 flush time with SUEZ.
INSP-Supply line flush6/16/20206/16/20206/16/2020PCANC
DetailsJim Page
Flush rescheduled for 17JUNE2020 per conversation with SUEZ and point of contact. Could not flush until water sample acceptance for the new water service.

Jeff Chaney is the contact. Thanks so much! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush6/12/20206/15/20206/15/2020PCANC
DetailsJim Page
Cancelled per conversation with point of contact, will be rescheduled for a later date.

Jeff Chaney is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/9/20206/9/20206/9/2020PPASS
DetailsTroy Cobbley
The two thrust blocks have been replaced. These sections of pipe can be covered.

Bryan Collins Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/8/20206/8/20206/8/2020PPART
DetailsTroy Cobbley
I gave the ok to cover on the remaining underground piping except for the two east most thrust blocks. These two thrust blocks have pulled/fallen away from the underground supply piping and will need to be repoured, re-inspected, prior to an ok for cover.

Bryan Collins is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in2/11/20202/12/20202/12/2020APART
DetailsJim Page
Rough to cover inspection for IBR complete, IBR approved for cover, remaining underground to be installed at a later date.

Bryan Collins is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
Issue and Print Permit  12/3/2019 DONE
Issue and Print Permit  12/3/2019 DONE
Sprinkler Plan Check11/27/2019 12/2/2019 PASS
DetailsMark Stumbaugh
1st review completed  12/2/2019 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  12/2/2019 DONE
DetailsMark Stumbaugh
Permit Ready to Issue  12/2/2019 DONE
met
Application received  11/27/2019 DONE
Application submitted via PDS Online on Nov 27 2019 7:59AM
Intake Approval  11/27/2019 PASS
DetailsMark Stumbaugh
Plan assigned to (Stumbaugh)11/27/2019 11/27/2019 DONE