INSP-Final Inspection | 7/17/2020 | 7/17/2020 | 7/17/2020 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection is complete.
Phone #: ###-#### Inspection requested via web by Robert Gobler
|
INSP-Final Inspection | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | FAIL |
Jim Page
|
|
|
Smoke detectors are over spaced, add/relocate as discussed, plans will need to be revisedand submitted for corrections. Provide map showing initiating devices and place at FACP.
Phone #: ###-#### Inspection requested via web by Robert Gobler
|
Plan resubmittals received | | | 7/14/2020 | | DONE |
|
|
|
Justin requested the work flow to be opened for as builts.
|
Plan assigned to (Lee) | 7/14/2020 | | 7/14/2020 | | DONE |
Lee G Meredith
|
|
|
as builts
|
Intake Approval | | | 7/14/2020 | | PASS |
|
|
|
|
1st review completed | | | 7/14/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 7/14/2020 | | 7/14/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 7/14/2020 | | DONE |
|
|
|
Plan mod passed. Minimum review time is due.
|
Permit Ready to Issue | | | 7/14/2020 | | DONE |
|
|
|
**PLAN MOD - DO NOT REISSUE**
|
CHANGE STATUS TO (ISS) | | | 7/14/2020 | | DONE |
|
|
|
|
INSP-Final Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 | P | FAIL |
Troy Cobbley
|
|
|
Need plan mods showing the communication method and the Sleeping area strobes need to meet NFPA 72 for the use of 110cd or 177cd as far as distance from ceiling as discussed. Need larger access to the east attic heat detector. Need the FACP shown upstairs instead of downstairs. Need to relocate or add a smoke detector in the basement as discussed. Plans show a PIV but none has been installed. See the city approved plans for corrections marked in red. No actual devices tested. Phone #: ###-#### Inspection requested via web by Robert Gobler
|
Intake Approval | | | 12/9/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 12/9/2019 | | 12/9/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/9/2019 | | DONE |
|
|
|
Passed as noted on drawings.
|
Permit Ready to Issue | | | 12/9/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 12/9/2019 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 12/3/2019 | | 12/3/2019 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 12/3/2019 | | FAIL |
|
|
|
Needs engineer of record approval and audible notifiation does not appear to be adequate. Returned to applicant.
12-4-19 Mary indicated that there are sounder bases so audibility will be adequate. She also noted that the engineer of record wont respond to her. I responded to say the engineer of record review / approval is required and that I need it by 12-5-19 before returning the submittal. Suggested that she contact the general contractor or architect.
12-5-19: No resubmittal with EOR approval so returned to Mary.
|
Application received | | | 12/2/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 2 2019 3:40PM
|