Permit Information
Permit NumberFIR19-00911
StatusIssued
Name TREASURE VALLEY FIRE PROTECTION
Site Address 111 W STATE ST
Project NameSt. Luke's Central Plant
Customer Number 
ePlanReviewYes
Description
Install a complete fire sprinkler system including a 1000 gpm fire pump and a seprate fire protection suppy to the NWPG
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Sprinkler Rough-in6/9/20206/9/20206/9/2020PPASS
DetailsTroy Cobbley
UG cover inspection passed from point of connection to the building footing/wall. Piping is ok for cover. Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
INSP-Sprinkler Rough-in4/15/20204/16/20204/16/2020APART
DetailsJim Page
Inspection for 2 heads above rewquested hardlid was completed via text pictures, rough to cover inspection for the 2 heads on Level G stariwell are complete, area of work is approved for cover.

2 heads above hard lid ceiling. Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
INSP-Sprinkler Rough-in/Hydro3/26/20203/27/20203/27/2020APART
DetailsJim Page
Rough in inspection for sections SB and G is complete, a follow up inspection will be required before final for possible obstructions.

randy Phone #: ###-####
INSP-Sprinkler Rough-in3/24/20203/26/20203/26/2020ACANC
DetailsJim Page
Cancel per Kerry Phone #: ###-#### >> Inspection requested via web by Lonnie Greenfield
Issue and Print Permit  12/20/2019 DONE
Sprinkler Plan Check12/18/2019 12/19/2019 FAIL
DetailsMark Stumbaugh
Plan resubmittals received  12/19/2019 PASS
DetailsMark Stumbaugh
Sprinkler Plan Check12/19/2019 12/19/2019 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  12/19/2019 DONE
DetailsMark Stumbaugh
Permit Ready to Issue  12/19/2019 DONE
met
Plan resubmittals received  12/18/2019 PASS
DetailsMark Stumbaugh
Sprinkler Plan Check12/6/2019 12/13/2019 FAIL
DetailsMark Stumbaugh
1st review completed  12/13/2019 FAIL
DetailsMark Stumbaugh
Intake Approval  12/6/2019 PASS
DetailsMark Stumbaugh
Plan assigned to (Stumbaugh)12/6/2019 12/6/2019 DONE
DetailsMark Stumbaugh
Application received  12/4/2019 DONE
Application submitted via PDS Online on Dec 4 2019 11:37AM