INSP-Supply line flush | 6/16/2020 | 6/17/2020 | 6/17/2020 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
This inspection is scheduled for 9:00 AM. Jim Baker is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/3/2020 | 6/4/2020 | 6/4/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for undergorund supply witnessed, no pressure loss observed at underground supply gauge.
Richard Clark is the contact(: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/31/2020 | 4/2/2020 | 4/1/2020 | A | CANC |
Jim Page
|
|
|
Talon is the contact. Thanks!(: Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 3/31/2020 | 4/2/2020 | 4/1/2020 | A | CANC |
Jim Page
|
|
|
Talon is the contact. Thanks for all your help(: Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 12/9/2019 | 12/10/2019 | 12/10/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
Bryan is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Issue and Print Permit | | | 12/6/2019 | | DONE |
|
|
|
|
Application received | | | 12/5/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 5 2019 12:07PM
|
Intake Approval | | | 12/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 12/5/2019 | | 12/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 12/5/2019 | | 12/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 12/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 12/5/2019 | | DONE |
|
|
|
met
|