INSP-Final Inspection | 1/22/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 12/25/2019 | 12/26/2019 | 12/26/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Intake Approval | | | 12/18/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 12/18/2019 | | 12/18/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 12/18/2019 | | 12/18/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 12/18/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/18/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 12/18/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/18/2019 | | DONE |
|
|
|
|
Application received | | | 12/16/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 16 2019 5:02PM
|