INSP-Sprinkler Rough-in | 2/11/2020 | 2/12/2020 | 2/12/2020 | P | PASS |
Jim Page
|
|
|
Previouly noted item has been corrected, plans reflect install. All tenting in place at time of inspection, overhead fire sprinkler piping rough in inspection is complete, cover is approved. Sticker for cover approval placed on window by main entry.
Phone #: ###-#### Inspection requested via web by Jonathan LaFond
|
Plan assigned to (Stumbaugh) | 1/31/2020 | | 2/3/2020 | | DONE |
Mark Stumbaugh
|
|
|
plan mod -revising piping plan due to building modifications per Jonathan Lafond
|
Sprinkler Plan Check | 2/3/2020 | | 2/3/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/3/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 1 hr
1 new device
|
Permit Ready to Issue | | | 2/3/2020 | | DONE |
|
|
|
plan mod met
|
CHANGE STATUS TO (ISS) | | | 2/3/2020 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 1/31/2020 | | DONE |
|
|
|
plan mod -revising piping plan due to building modifications per Jonathan
|
INSP-Sprinkler Rough-in | 1/30/2020 | 1/30/2020 | 1/30/2020 | P | FAIL |
Jim Page
|
|
|
Changes had to be made to head coverage due too beam layout, need to have city approved plans match what was installed.
Phone #: ###-#### Inspection requested via web by Jonathan LaFond
|
Intake Approval | | | 1/7/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/7/2020 | | 1/7/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 1/7/2020 | | 1/7/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 1/7/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 1/7/2020 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 1/7/2020 | | DONE |
|
|
|
|
Application received | | | 12/26/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 26 2019 10:12AM
|