INSP-Final Inspection | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
jon Phone #: ###-####
|
Plan Modification Accepted | | | 2/6/2020 | | DONE |
|
|
|
John from All Valley Fire requested the workflow to be opened for a plan mod
|
Plan assigned to (Stumbaugh) | 2/6/2020 | | 2/6/2020 | | DONE |
Mark Stumbaugh
|
|
|
plan mod
|
Sprinkler Plan Check | 2/6/2020 | | 2/6/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2020 | | PASS |
Mark Stumbaugh
|
|
|
No review fee
No new devices
|
Permit Ready to Issue | | | 2/6/2020 | | DONE |
|
|
|
plan mod approved
|
CHANGE STATUS TO (ISS) | | | 2/6/2020 | | DONE |
|
|
|
plan mod approved
|
INSP-Sprinkler Rough-in | 2/4/2020 | 2/5/2020 | 2/4/2020 | A | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Jonathan LaFond Inspection cancelled from web by: Jonathan LaFond
|
INSP-Sprinkler Rough-in | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for All Valley scope of work is complete, scope of work is approved for cover at contractors discertion. Will need to verify calculations to support more than 1 head off of 1 inch piping, numerous areas throughout the existing section of tenant space have more than 1 head off of 1 inch pipe and approved plans show only 1 head off of 1 inch piping, corrections may be required. Need to verify compatibility between concelaed fusible link heads and the 155 quick response glass bulb heads, concealer heads are shown as 155 quick response heads on city approved drawings. A seperate rough in inspection will be required before final inspection to verify more than 1 head off of 1 inch piping as well as concealed/recessed head compatability.
peyton Phone #: ###-####
|
Issue and Print Permit | | | 1/10/2020 | | DONE |
|
|
|
|
Application received | | | 1/9/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 9 2020 10:58AM
|
Intake Approval | | | 1/9/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/9/2020 | | 1/9/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 1/9/2020 | | 1/9/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 1/9/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 1/9/2020 | | DONE |
|
|
|
met
|