INSP-Final Inspection | 5/12/2020 | 5/15/2020 | 5/15/2020 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for scope of work is complete.
Please call 30 minutes prior to arrival so we can make sure we can get in Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 1/29/2020 | 1/29/2020 | 1/29/2020 | P | DONE |
Troy Cobbley
|
|
|
PASS rough ok to cover**MAS
Phone #: ###-#### >> Inspection requested via web by Sam Ball
|
Intake Approval | | | 1/29/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/29/2020 | | 1/29/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 1/29/2020 | | 1/29/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 1/29/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 1/29/2020 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 1/29/2020 | | DONE |
|
|
|
|
Application received | | | 1/27/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 27 2020 3:56PM
|