INSP-Final Inspection | 3/16/2020 | 3/16/2020 | 3/16/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Call James before heading out, ready any time. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 3/12/2020 | 3/13/2020 | 3/13/2020 | A | CANC |
Troy Cobbley
|
|
|
Not ready for final. Need rough-in passed.
Please call James before heading out, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 3/12/2020 | 3/13/2020 | 3/13/2020 | A | FAIL |
Troy Cobbley
|
|
|
Installation appeared ok but there were no approved plans or small documents on site.
Please call James before heading out, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Issue and Print Permit | | | 2/11/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/6/2020 | | 2/7/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 2/7/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/7/2020 | | DONE |
|
|
|
met
|
Application received | | | 2/6/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 6 2020 11:32AM
|
Intake Approval | | | 2/6/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/6/2020 | | 2/6/2020 | | DONE |
Mark Stumbaugh
|
|
|
|