INSP-Final Inspection | 5/13/2020 | 5/13/2020 | 5/13/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Contact is Dan. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
CHANGE STATUS TO (ISS) | | | 5/13/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/12/2020 | | DONE |
|
|
|
Hailey requested the workflow to be open for as builts #2
|
Plan assigned to (Lee) | 5/12/2020 | | 5/12/2020 | | DONE |
Lee G Meredith
|
|
|
as builts #2
|
Intake Approval | | | 5/12/2020 | | PASS |
|
|
|
|
1st review completed | | | 5/12/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 5/12/2020 | | 5/12/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/12/2020 | | DONE |
|
|
|
Corrections to as builts - No Fee.
|
Permit Ready to Issue | | | 5/12/2020 | | DONE |
|
|
|
**AS BUILT - DO NOT REISSUE**
|
INSP-Final Inspection | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need monitor modules installed and as-builts showing the installation of the monitor modules for the trouble signals from the dry pipe sprinkler system accelerators. Per tech they worked wednesday. This piece of equipment needs to be monitored per IFC 903.4. Also need the map updated showing all initiating devices. Need NFPA 72 Record of Completion.
Contact is Dan. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
CHANGE STATUS TO (REV) | | | 5/7/2020 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 5/7/2020 | | 5/7/2020 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 5/7/2020 | | PASS |
|
|
|
|
1st review completed | | | 5/7/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 5/7/2020 | | 5/7/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/7/2020 | | DONE |
|
|
|
As built - No Fee.
As built subitted 5-5-20 but did not get into the approved file due to server failures. Resubmitted to be reporcessed.
|
Permit Ready to Issue | | | 5/7/2020 | | DONE |
|
|
|
as built
|
CHANGE STATUS TO (ISS) | | | 5/7/2020 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 4/20/2020 | | 5/5/2020 | | DONE |
Lee G Meredith
|
|
|
as builts
|
Intake Approval | | | 5/5/2020 | | PASS |
|
|
|
|
1st review completed | | | 5/5/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 5/5/2020 | | 5/5/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/5/2020 | | DONE |
|
|
|
As built - No Fee
|
Plan resubmittals received | | | 4/20/2020 | | DONE |
|
|
|
Hailey with Protex requesting as builts
|
INSP-Final Inspection | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | FAIL |
Troy Cobbley
|
|
|
The office area ceiling mounted strobes are overspaced. The truss mounted strobes in the warehouse area are overspaced. No testing performed. Need ceiling installed in the NAC panel room so the smoke detector works.
Contact is Dan. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 4/16/2020 | 4/17/2020 | 4/16/2020 | A | CANC |
Troy Cobbley
|
|
|
Contact is Dan. Phone #: ###-#### >> Inspection requested via web by Morgan Ahten Inspection cancelled from web by: Morgan Ahten
|
Plan assigned to (Lee) | 2/24/2020 | | 2/24/2020 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 2/24/2020 | | FAIL |
|
|
|
Missing scale graph
|
1st review completed | | | 2/24/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 2/24/2020 | | 2/24/2020 | | PASS |
Lee G Meredith
|
|
|
Passed as noted on drawing.
|
PLANS TAKEN FRONT DESK ALARM | | | 2/24/2020 | | DONE |
|
|
|
Passed with review comments.
|
Permit Ready to Issue | | | 2/24/2020 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/24/2020 | | DONE |
|
|
|
|
Application received | | | 2/12/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 12 2020 2:12PM
|