CHANGE STATUS TO (ISS) | | | 4/29/2020 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 4/23/2020 | | 4/24/2020 | | DONE |
Lee G Meredith
|
|
|
as built -update the reser for the addition of an addressable module for the pressure switch.
|
Intake Approval | | | 4/24/2020 | | PASS |
|
|
|
|
1st review completed | | | 4/24/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 4/24/2020 | | 4/24/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 4/24/2020 | | DONE |
|
|
|
Corrected as built.
|
Permit Ready to Issue | | | 4/24/2020 | | DONE |
|
|
|
**AS BUILT - DO NOT REISSUE**
|
Plan resubmittals received | | | 4/23/2020 | | DONE |
|
|
|
as built request by Hailey Ahten see Doc email.
|
INSP-Final Inspection | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | PART |
Troy Cobbley
|
|
|
A temp for fire alarm until the plans are submitted showing the added/changed module on the low air switch. All devices tested ok.
Contact is Davis. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | FAIL |
Troy Cobbley
|
|
|
Actually went to the project site twice today. The first trip the descripters from the device to the panel did not match. Low air came in as an alarm and rang the bell. Came back the second time and the monitoring company descriptors do not match. Will need to reschedule for tomorrow and a re-inspection fee has been applied. Contact is Davis. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Plan assigned to (Lee) | 4/17/2020 | | 4/20/2020 | | DONE |
Lee G Meredith
|
|
|
as builts
|
1st review completed | | | 4/20/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 4/20/2020 | | 4/20/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 4/20/2020 | | DONE |
|
|
|
As built - No fee. Previous as built submittal did not show the stamp on one of the drawings.
|
Permit Ready to Issue | | | 4/20/2020 | | DONE |
|
|
|
as built approved (stamped drawing that was missed in the last as built per LGM)
|
CHANGE STATUS TO (ISS) | | | 4/20/2020 | | DONE |
|
|
|
|
INSP-Final Inspection | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | FAIL |
Troy Cobbley
|
|
|
The signal reports show a different designation for alarms than what is tested, old fire alarm devices need removed, the facp installed does not match the facp submitted, the basement plan has no stamp on it, the riser sheet was not provided. No devices tested.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Plan resubmittals received | | | 4/17/2020 | | DONE |
|
|
|
Morgan with protex opening up for asbuilts
|
CHANGE STATUS TO (ISS) | | | 4/17/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/16/2020 | | DONE |
|
|
|
Hailey from Protex requesting to open workflow for asbuilts
|
Plan assigned to (Lee) | 4/16/2020 | | 4/16/2020 | | DONE |
Gabe Brenner
|
|
|
as builts
|
1st review completed | | | 4/16/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 4/16/2020 | | 4/16/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 4/16/2020 | | DONE |
|
|
|
As built - No fee.
|
Permit Ready to Issue | | | 4/16/2020 | | DONE |
|
|
|
**DO NOT REISSUE - AS BUILT**
|
Permit Ready to Issue | | | 2/19/2020 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 2/19/2020 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 2/18/2020 | | 2/18/2020 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 2/18/2020 | | PASS |
|
|
|
|
1st review completed | | | 2/18/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 2/18/2020 | | 2/18/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/18/2020 | | DONE |
|
|
|
Passed with review comments.
|
Application received | | | 2/13/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 13 2020 1:55PM
|