INSP-Final Inspection | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete, irrigation shutoff witnessed during flow switch activation.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in/Hydro | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test witnessed at city pressure with no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | CANC |
Jim Page
|
|
|
screened // Jonathan Phone #: ###-#### Inspection cancelled from web by: Jonathan Lee
|
INSP-Sprinkler Rough-in | 5/22/2020 | 5/26/2020 | 5/26/2020 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover is approved. Cover approval sticker has been placed.
tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Conference | 5/19/2020 | 5/21/2020 | 5/21/2020 | A | DONE |
Jim Page
|
|
|
Fire conference is complete, provided information for irrigation shut-down on flow switch activation.
meeting with super and electrician to explain irrigation shut off procedure. Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 5/16/2020 | 5/18/2020 | 5/18/2020 | P | PART |
Jim Page
|
|
|
Rough in inspection is complete, one head was to close to wall, will verify relocation during tenting inspection. No tenting installed at time of inspection, no cover is approved.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
CHANGE STATUS TO (ISS) | | | 5/13/2020 | | DONE |
|
|
|
|
Plan assigned to (Stumbaugh) | 3/23/2020 | | 5/11/2020 | | DONE |
Mark Stumbaugh
|
|
|
as builts
|
Plan Modification Accepted | | | 5/11/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 5/11/2020 | | 5/11/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/11/2020 | | DONE |
Mark Stumbaugh
|
|
|
1 hr revierw time
no new devices
|
Permit Ready to Issue | | | 5/11/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/23/2020 | | DONE |
|
|
|
Tom required the workflow to be reopened for as builts.
|
Issue and Print Permit | | | 3/20/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/24/2020 | | 2/28/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 2/28/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/28/2020 | | DONE |
|
|
|
|
Application received | | | 2/24/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 24 2020 9:38AM
|
Intake Approval | | | 2/24/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/24/2020 | | 2/24/2020 | | DONE |
Mark Stumbaugh
|
|
|
|