INSP-Sprinkler Rough-in | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for scope of work is complete, cover is approved. Fire sprinkler head to be added above cooler to cover exposed combustible material, will verify head addition on next inspection.
Tony Cetani is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Permit Ready to Issue | | | 7/17/2020 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 7/17/2020 | | DONE |
|
|
|
|
Intake Approval | | | 7/16/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/16/2020 | | 7/16/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/16/2020 | | 7/16/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 7/16/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/16/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 2/27/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 27 2020 7:59AM
|
Intake Approval | | | 2/27/2020 | | FAIL |
Mark Stumbaugh
|
|
|
waiting for BLD to be issued
|