INSP-Final Inspection | 3/27/2020 | 3/27/2020 | 3/27/2020 | P | FAIL |
Troy Cobbley
|
|
|
Dialer tested. Permit will need to be rescheduled for a final when test papers are received.
Phone #: ###-#### Inspection requested via web by Robert Gobler
|
INSP-Final Inspection | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans on site.
Phone #: ###-#### Inspection requested via web by Robert Gobler
|
1st review completed | | | 3/11/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 3/11/2020 | | 3/11/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/11/2020 | | DONE |
|
|
|
Quick permit passed. No review comments.
|
Permit Ready to Issue | | | 3/11/2020 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 3/11/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/9/2020 | | DONE |
|
|
|
Resubmittal did not have the requested changes. I emailed Robert to have him make the changes and email directly to me.
|
Plan assigned to (Lee) | 3/6/2020 | | 3/6/2020 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 3/6/2020 | | FAIL |
|
|
|
Robert is to include alarm and supervisory conditions to the operational matrix and resubmit.
|
Application received | | | 3/5/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 5 2020 6:29PM
|