INSP-Supply line flush | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | DONE |
Jim Page
|
|
|
Main underground supply flush witnessed.
*Screened* Underground Troy, requesting 6AM Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2020 | 5/19/2020 | 5/19/2020 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro witnessed with no pressure loss. Please contact Troy Nelson for underground Hydro Test for an afternoon inspection. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok for cover. Please contact Troy Nelson for time of afternoon inspection. This a rough-in to cover underground service. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
Issue and Print Permit | | | 5/1/2020 | | DONE |
|
|
|
|
Intake Approval | | | 4/30/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/30/2020 | | 4/30/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/30/2020 | | 4/30/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 4/30/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/30/2020 | | DONE |
|
|
|
met
|
Intake Approval | | | 3/9/2020 | | FAIL |
Mark Stumbaugh
|
|
|
No trade permits can be issued until a building permit is issued.
Resubmit once BLD19-04682 is issued.
|
Application received | | | 3/6/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 6 2020 8:29AM
|