INSP-Sprinkler Rough-in | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | PASS |
Troy Cobbley
|
|
|
The remaining sprinkler piping is ok for cover. Rough-in passed.
Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 8/3/2020 | 8/4/2020 | 8/4/2020 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow morning. Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 5/26/2020 | 5/26/2020 | 5/26/2020 | P | PASS |
Troy Cobbley
|
|
|
Piping above the lay-in tile is ok for cover. Look at gridded rooms for cover. Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Sprinkler Rough-in | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for piping/heads marked "ok" that are ok for cover. Phone #: ###-#### Inspection requested via web by Sam Ball
|
Intake Approval | | | 3/20/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/20/2020 | | 3/20/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 3/20/2020 | | 3/20/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 3/20/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 3/20/2020 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 3/20/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/19/2020 | | FAIL |
Mark Stumbaugh
|
|
|
Waiting on BLD to be issued
|
Application received | | | 3/11/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 11 2020 12:20PM
|