INSP-Final Inspection | 8/11/2020 | 8/12/2020 | 8/12/2020 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for a final yet. Inspection turned into a conference to address several areas that will need the notification adjusted and/or added due to partial height walls with curtains and chalk boards. Provide verification that all current draw for existing devices has been included in calcs.
Contact is Dan. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 6/9/2020 | 6/10/2020 | 6/10/2020 | A | CANC |
Troy Cobbley
|
|
|
Inspection was not for a final but was a conference on strobe coverage in the remodel area. It appears some of the strobes will be blocked by duct work.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Issue and Print Permit | | | 4/2/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/1/2020 | | DONE |
|
|
|
|
1st review completed | | | 4/1/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 4/1/2020 | | 4/1/2020 | | PASS |
Lee G Meredith
|
|
|
Passed as noted.
|
PLANS TAKEN FRONT DESK ALARM | | | 4/1/2020 | | DONE |
|
|
|
Passed with review comments and requirements.
|
Permit Ready to Issue | | | 4/1/2020 | | DONE |
|
|
|
met
|
Plan assigned to (Lee) | 3/19/2020 | | 3/19/2020 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 3/19/2020 | | PASS |
|
|
|
|
1st review completed | | | 3/19/2020 | | FAIL |
|
|
|
Visible notification does not appear to be adequate, new devices need to be noted with (N) and areas not within the "Area of Work" need to be noted to insure clarity at the time of inspection.
|
Application received | | | 3/17/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 17 2020 12:07PM
|