INSP-Final Inspection | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Project Manager Randy Burkland Store requiring vendors where maks Phone #: ###-#### Inspection requested via web by Bruce Sullivan
|
INSP-Final Inspection | 4/28/2020 | 4/29/2020 | 4/29/2020 | A | FAIL |
Troy Cobbley
|
|
|
For a final we need to test the last two duct smoke detectors, test PIV and retest the water soaked backflow tamper switch.
Project Manager Randy Burkland Store now requiring vendors to were face mask and check in at store Phone #: ###-#### Inspection requested via web by Bruce Sullivan
|
Issue and Print Permit | | | 4/24/2020 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 4/22/2020 | | 4/23/2020 | | DONE |
Lee G Meredith
|
|
|
plan mod
|
Intake Approval | | | 4/23/2020 | | PASS |
|
|
|
|
1st review completed | | | 4/23/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 4/23/2020 | | 4/23/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 4/23/2020 | | DONE |
|
|
|
Plan mod passed. No additional review comments.
Minimum review fee of $65 is due.
|
Permit Ready to Issue | | | 4/23/2020 | | DONE |
|
|
|
plan mod approved
|
Plan Modification Accepted | | | 4/22/2020 | | DONE |
|
|
|
Bruce with integrated seccurity solutions is requesting to open workflow for plan modification. - adding more devices
|
INSP-Final Inspection | 4/15/2020 | 4/17/2020 | 4/17/2020 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was a walk through to check notification devices. See city approved plans for correction needed. Plan mods will be required. No actual testing of devices happened today.
Randy Burkland - Project manager Phone #: ###-#### Inspection requested via web by Bruce Sullivan
|
Alarm Plan Check | 3/25/2020 | | 3/25/2020 | | PASS |
Lee G Meredith
|
|
|
|
Plan resubmittals received | | | 3/25/2020 | | DONE |
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/25/2020 | | DONE |
|
|
|
Quick permit passed. No review comments.
|
Permit Ready to Issue | | | 3/25/2020 | | DONE |
|
|
|
MET
|
Issue and Print Permit | | | 3/25/2020 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 3/23/2020 | | 3/23/2020 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 3/23/2020 | | PASS |
|
|
|
|
1st review completed | | | 3/23/2020 | | FAIL |
|
|
|
Candela is not noted onadded visible devices. Informed Bruce of this via email.
|
Application received | | | 3/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2020 12:34PM
|