INSP-Sprinkler Rough-in | 7/9/2020 | 7/13/2020 | 7/13/2020 | A | PART |
Troy Cobbley
|
|
|
I left a correction notice the heat/insulation will be required to maintain a 40 degree min. as per NFPA 13. I also noted that the current approved plans do not match the installation. Mike Martin is the contact. Thank you Phone #: ###-#### Inspection requested via web by jeremiah robison
|
Issue and Print Permit | | | 3/25/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/23/2020 | | 3/24/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 3/24/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/24/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 3/24/2020 | | DONE |
|
|
|
met
|
Intake Approval | | | 3/23/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/23/2020 | | 3/23/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 3/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2020 2:35PM
|