INSP-Sprinkler Rough-in | 5/14/2020 | 5/14/2020 | 5/14/2020 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area A complete, area A approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2020 | 5/14/2020 | 5/14/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping in area A witnessed, no pressure loss observed at riser provided gauge.
Call Steve Johnson cell 208.598.5155 for escort, meet in B26 Lobby. Phone #: ###-#### Inspection requested via web by Steve Johnson
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2020 | 5/12/2020 | 5/11/2020 | A | CANC |
Jim Page
|
|
|
Call Steve Johnson cell ###-#### for escort, meet in B26 Lobby. Phone #: ###-#### >> Inspection requested via web by Steve Johnson Inspection cancelled from web by: Steve Johnson
|
Issue and Print Permit | | | 4/17/2020 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/17/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/16/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/16/2020 | | 4/16/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/16/2020 | | DONE |
|
|
|
|
Intake Approval | | | 4/6/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/6/2020 | | 4/6/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/6/2020 | | 4/6/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Application received | | | 4/3/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 3 2020 9:51AM
|