INSP-Sprinkler Rough-in | 6/22/2020 | 6/22/2020 | 6/22/2020 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining area of work complete, approved for cover.
screened // Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 5/5/2020 | 5/5/2020 | 5/5/2020 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for hardlids in area of work complete, hardlids approved for cover.
Jon Olmstead Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
Issue and Print Permit | | | 4/16/2020 | | DONE |
|
|
|
|
Application received | | | 4/15/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 15 2020 9:35AM
|
Intake Approval | | | 4/15/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/15/2020 | | 4/15/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/15/2020 | | 4/15/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 4/15/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/15/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/15/2020 | | DONE |
|
|
|
met
|