INSP-Final Inspection | 8/7/2020 | 8/7/2020 | 8/7/2020 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
Justin Nelson is our foreman Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
CHANGE STATUS TO (ISS) | | | 7/21/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/16/2020 | | |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
Plan assigned to (Stumbaugh) | 7/14/2020 | | 7/15/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/15/2020 | | 7/15/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 1hr
3 new devices
|
Plan Modification Accepted | | | 7/14/2020 | | DONE |
|
|
|
Brad at Treasure Valley Fire opening up for plan mod - Adding more equipment
|
INSP-Sprinkler Rough-in | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | PART |
Jim Page
|
|
|
Rough in inspection for paint booth area is complete, sprinklers will be required in second phase of the painting/baking operation.
ADAM IS OUR FOREMAN Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Final Inspection | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | PART |
Jim Page
|
|
|
Final inspection for paint booth area is complete, sprinklers will be required in second phase of the painting/baking operation.ADAM IS OUR FOREMAN Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
Issue and Print Permit | | | 6/29/2020 | | DONE |
|
|
|
|
Intake Approval | | | 6/22/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/22/2020 | | 6/22/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/22/2020 | | 6/22/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 6/22/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/22/2020 | | DONE |
|
|
|
|
Application received | | | 4/15/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 15 2020 1:31PM
|