INSP-Final Inspection | 8/10/2020 | 8/10/2020 | 8/10/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete, irrigation shut-down on flow switch activation witnessed.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/26/2020 | 5/26/2020 | 5/26/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test witnessed, no pressure loss observed at riser provided gauge.
Rough, hydro, tenting ready this afternoon. Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 5/26/2020 | 5/26/2020 | 5/26/2020 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping is complete. All tenting was in place at time of inspection. A cover sticker has been placed for cover approval. Cover is approved.
|
Issue and Print Permit | | | 5/20/2020 | | DONE |
|
|
|
|
Intake Approval | | | 5/19/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 5/19/2020 | | 5/19/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 5/19/2020 | | 5/19/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 5/19/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/19/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 5/19/2020 | | DONE |
|
|
|
|
Application received | | | 5/18/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 18 2020 4:16PM
|