INSP-Sprinkler Rough-in | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | PART |
Jim Page
|
|
|
Rough to cover inspection from between south connection too tank (Still about 10 feet of pipe left to install by tank) around too approxiamatly 5 sticks of pipe on north section complete (north piping runs west too east) complete, area inspected approved for cover.
Please call Clarence for the rough in on the underground. Phone #: ###-#### Inspection requested via web by Jessia McLain
|
INSP-Sprinkler Rough-in | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | PART |
Troy Cobbley
|
|
|
The 14" underground piping, between the two 45's on the southwest corner of the project is ok for cover.
Partial rough in on underground. Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia McLain
|
Permit Ready to Issue | | | 7/20/2020 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/20/2020 | | DONE |
|
|
|
|
Intake Approval | | | 7/17/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/17/2020 | | 7/17/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/17/2020 | | 7/17/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 7/17/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 6/3/2020 | | FAIL |
Mark Stumbaugh
|
|
|
Waiting for BLD20-01457 permit to be issued
|
Application received | | | 6/2/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 2 2020 7:53PM
|