INSP-Sprinkler Rough-in | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover is approved. Cover sticker has been placed.
tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 8/3/2020 | 8/3/2020 | 8/3/2020 | P | PART |
Jim Page
|
|
|
Rough in inspection is complete, no tenting installed at time of inspection, cover is not approved.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
Plan resubmittals received | | | 7/31/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/31/2020 | | 7/31/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 1hr
no new devices
|
Permit Ready to Issue | | | 7/31/2020 | | DONE |
|
|
|
MET
|
CHANGE STATUS TO (ISS) | | | 7/31/2020 | | DONE |
|
|
|
|
Plan assigned to (Stumbaugh) | 7/28/2020 | | 7/30/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 7/30/2020 | | FAIL |
Mark Stumbaugh
|
|
|
Plans are mirrored from what is on site.
|
Plan resubmittals received | | | 7/28/2020 | | DONE |
|
|
|
as builts requested per Tom
|
Issue and Print Permit | | | 7/6/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/18/2020 | | 6/22/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 6/22/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/22/2020 | | DONE |
|
|
|
|
Intake Approval | | | 6/18/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/18/2020 | | 6/18/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 6/16/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 16 2020 5:18PM
|