INSP-Sprinkler Rough-in/Hydro | 8/5/2020 | 8/5/2020 | 8/5/2020 | A | FAIL |
Jim Page
|
|
|
System could not have hydro performed, cap above furnace closet was cut and removed by others, a re-hydro will be required after repair is made.
|
Fees Due Hold | 8/4/2020 | | 8/4/2020 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 8/3/2020 | 8/3/2020 | 8/3/2020 | P | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, rough in inspection is complete, all tenting in place at time of inspection. Cover is approved, cover sticker has been placed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
Permit Ready to Issue | | | 7/31/2020 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
CHANGE STATUS TO (ISS) | | | 7/31/2020 | | DONE |
|
|
|
|
Plan assigned to (Stumbaugh) | 7/29/2020 | | 7/30/2020 | | DONE |
Mark Stumbaugh
|
|
|
as builts
|
Sprinkler Plan Check | 7/30/2020 | | 7/30/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review time 1 hr
No new devices
|
INSP-Sprinkler Rough-in | 7/28/2020 | 7/29/2020 | 7/29/2020 | A | FAIL |
Jim Page
|
|
|
Install does not match city approved drawings.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
Plan resubmittals received | | | 7/29/2020 | | DONE |
|
|
|
Tom requested as builts
|
Issue and Print Permit | | | 7/6/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/19/2020 | | 6/23/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 6/23/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/23/2020 | | DONE |
|
|
|
MET
|
Intake Approval | | | 6/19/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/19/2020 | | 6/19/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 6/18/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 18 2020 8:55PM
|