INSP-Final Inspection | 7/28/2020 | 7/29/2020 | 7/29/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Contact Andrew Larson ###-#### 30 min prior to Fire Final Insp start please, Andrew is requesting a 12 PM inspection time if at all possible.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/22/2020 | 7/22/2020 | 7/22/2020 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
Contact Andrew Larson ###-#### 30 Min prior to RTC Insp start please he requested an 11 AM insp time ... I inadvertently shceduled on wrong permit number.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
Issue and Print Permit | | | 7/16/2020 | | DONE |
|
|
|
|
Intake Approval | | | 7/15/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/15/2020 | | 7/15/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/15/2020 | | 7/15/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 7/15/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 7/15/2020 | | DONE |
|
|
|
|
Application received | | | 7/14/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 14 2020 12:26PM
|