INSP-Final Inspection | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 8/14/2001 4:41:37 PM
|
DOC - Permit Finaled | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 8/14/2001 4:42:08 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/16/2000 | 10/16/2000 | 10/16/2000 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/16/2000 at 08:43:57. Contact: ###-####. hydro test okay; still need to verifyexisting tampers and flow with the new alarm panel 10/16/2000 2:35:32 PM
|
INSP-Conference | 6/28/2000 | 6/29/2000 | 6/29/2000 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/28/2000 at 14:39:59. Contact: ###-####. reqested infor on F/S damper activation 6/30/00 8:09:50 AM
|
INSP-Conference | 3/21/2000 | 3/21/2000 | 3/21/2000 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/21/2000 at 08:24:06. Contact: ###-####. Ok to cover various hard lid areas 3/22/00 9:21:59 AM
|
INSP-Conference | 3/14/2000 | 3/16/2000 | 3/16/2000 | P | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/14/2000 at 09:38:29. Contact: ###-####. Will reschedule for 3/17/00 3/17/00 10:39:45 AM
|
INSP-Conference | 2/2/2000 | 2/3/2000 | 2/3/2000 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/02/2000 at 15:46:06. Contact: ###-####. Location of annuunciat?? panel. 2/4/00 11:11:13 AM
|
INSP-Conference | 1/26/2000 | 1/27/2000 | 1/27/2000 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 01/26/2000 at 09:29:18. Contact: ###-####. okay to cover north addition 1/28/00 8:36:07 AM
|
INSP-Sprinkler Rough-in | 12/22/1999 | 12/22/1999 | 12/22/1999 | P | PART |
Rick Jackson
|
|
|
special needs and janitor closet okay to cover
|
INSP-Conference | 12/21/1999 | 12/21/1999 | 12/21/1999 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/21/1999 at 09:51:48. Contact: ###-####. Met with general contractor about canceled spaces and sprinklers.
|
INSP-Sprinkler Rough-in/Hydro | 11/18/1999 | 11/18/1999 | 11/18/1999 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/18/1999 at 09:00:39. Contact: ###-####. Ok to cover 2nd floor- room west of elevator shaft.
|
INSP-Supply line flush | 10/14/1999 | 10/15/1999 | 10/15/1999 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/14/1999 at 11:53:49. Contact: ###-####. Underground hydro test- pass
|
INSP-Supply line flush | 10/11/1999 | 10/12/1999 | 10/12/1999 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/11/1999 at 14:42:06. Contact: ###-####. Underground flush okay
|
INSP-Supply line flush | 10/5/1999 | 10/8/1999 | 10/8/1999 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/05/1999 at 08:11:58. Contact: ###-####. Underground cover iinspection - okay
|
INSP-Sprinkler Rough-in | 9/22/1999 | 9/23/1999 | 9/23/1999 | A | PASS |
Rick Jackson
|
|
|
RICK-- ###-#### --UNGROUND INSP - Underground inspection for 10 feet stubbed out from building okay to cover - reinspect the remainder of line to street and thrust blocks
|
Insp Record Card- SPRINKLER | | | 8/2/1999 | | |
|
|
|
|
Issue permit | | | 8/2/1999 | | |
|
|
|
|
Telephone call | | | 8/2/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/1999 | | |
|
|
|
|
Fire Sprinkler Plan Check | 7/30/1999 | | 7/30/1999 | | PASS |
|
|
|
|
Application received | | | 7/22/1999 | | PASS |
|
|
|
|