DOC - Permit Finaled | | | 8/1/2001 | | DONE |
Rick Jackson
|
|
|
For Joe Tawney
|
INSP-Final Inspection | 2/7/2001 | 2/7/2001 | 2/7/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 2/7/2001 9:39:22 AM
|
INSP-Sprinkler Rough-in/Hydro | 10/11/2000 | 10/13/2000 | 10/13/2000 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/11/2000 at 16:38:59. Contact: ###-####. okay to cover 10/13/2000 9:38:06 AM
|
INSP-Supply line flush | 4/11/2000 | 4/14/2000 | 4/14/2000 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 04/11/2000 at 15:42:22. Contact: ###-####. Flush ok 4/17/00 1:52:03 PM
|
INSP-Supply line flush | 1/12/2000 | 1/12/2000 | 1/12/2000 | P | PART |
Rick Jackson
|
|
|
underground okay to cover - flush needed
|
Issue permit | | | 12/6/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | 12/1/1999 | 12/1/1999 | 12/1/1999 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/30/1999 | | 11/30/1999 | | PASS |
|
|
|
|
Miscellaneous action | | | 11/30/1999 | | PASS |
|
|
|
PLANS TAKEN TO FRON DESK.
|
Telephone call | | | 11/29/1999 | | FAIL |
|
|
|
Called Bob Knight, designer. Not in. Left message that I cannot follow calcs on 4 head loops.
|
Sprinkler Plan Check | 11/23/1999 | | 11/29/1999 | | FAIL |
|
|
|
Cannot follow calcs on 4 head loops.
|
Application received | | | 11/23/1999 | | PASS |
|
|
|
|
Case Summary | | | | | |
|
|
|
|