GCB-Final | 6/21/2010 | 6/22/2010 | 6/22/2010 | A | PASS |
Dave Hannah
|
|
|
|
GCB-Fndatn/slab ins/fld vent | 12/1/2009 | 12/2/2009 | 12/2/2009 | A | PASS |
Mike Jordan
|
|
|
contact Dale@###-####. Approved plans have been provided, remainder of framing ok. Energy code inspection also ok. Ok to cover.
|
GCB-Framing | 11/30/2009 | 12/1/2009 | 12/1/2009 | A | PASS |
Mike Jordan
|
|
|
Contact Dale @###-####Home owner@###-####. ok to insul. Needs to provide approved plans on energy inspection.
|
GCB-Fire Wall | 10/23/2009 | 10/26/2009 | 10/26/2009 | A | PASS |
Mike Jordan
|
|
|
Contact Nate@###-####. Double layer 5/8 type x rock at soffits ok.
|
GCB-Energy | 9/24/2009 | 9/25/2009 | 9/28/2009 | | PASS |
Mike Jordan
|
|
|
Block 14 Contact ####-####. Rigigd foam insulation at interior of stemwall ok.
|
GCB-Footing | 9/16/2009 | 9/16/2009 | 9/16/2009 | P | PASS |
Mike Jordan
|
|
|
Permiter footings ok. Setbacks as per approved plans.
|
Issue and Courier | | | 9/9/2009 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 9/4/2009 | 9/4/2009 | 9/8/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 9/4/2009 | | 9/8/2009 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 9/8/2009 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/8/2009 | | DONE |
Sam Zahorka
|
|
|
|
Application received | | 9/4/2009 | | | |
|
|
|
|