GCB-Final | 11/23/2009 | 11/24/2009 | 11/24/2009 | A | PASS |
Dave Hannah
|
|
|
Contact Lee @###-#### or ###-####Please call Lee prior to come in for inspection.
|
GCB-Framing | 11/19/2009 | 11/20/2009 | 11/20/2009 | A | PART |
Dave Hannah
|
|
|
Contact Lee @###-#### or ###-####Please call Lee priot come in for inspection. needs to add holddown clips on everyother truus
|
Plan assigned to (SRZ) | 9/24/2009 | 9/24/2009 | 10/13/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 10/13/2009 | | 10/13/2009 | | PASS |
Sam Zahorka
|
|
|
Received evaluation letter from Performance Engineers demonstrating compliance of nonconventional elements are compatible with the performance of a conventional framed system. Letter has been attached to this permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2009 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 10/13/2009 | | DONE |
|
|
|
|
Telephone call | | | 10/8/2009 | | DONE |
Sam Zahorka
|
|
|
I called the applicant Mr. Lee Healy to follow up on the corrections that were requested to complete his review. I suggested I call his engineer to try to resolve the pending issues with his project. He gave me his engineers telephone number and I offered to call him and email the correction report to him to resolve permitting issues.
SRZ
|
Telephone call | | | 9/28/2009 | | DONE |
|
|
|
left vm for jenah at ###-#### - permit plan review failed - will have plans returned to GC for resubmittal
|
Routing - PLAN CHECK | 9/24/2009 | | 9/25/2009 | | FAIL |
Sam Zahorka
|
|
|
Corrections needed on plans. Correction Report sent to Garden City.
|
1st review completed | | | 9/25/2009 | | FAIL |
Sam Zahorka
|
|
|
|
Plan resubmittals requested | | | 9/25/2009 | | DONE |
Sam Zahorka
|
|
|
Emailed Plan review correction report to Garden City.
|
Case Summary (GCB) | | | 9/25/2009 | | DONE |
Sam Zahorka
|
|
|
|
Application received | | 9/24/2009 | | | |
|
|
|
|