GCB-Final | 8/21/2012 | 8/22/2012 | 8/22/2012 | A | PASS |
Mike Jordan
|
|
|
Jeremy @ ###-#### As early in the morning as possible please. Ok for perm occ. All issues have been resolved.
|
GCB-Final | 8/20/2012 | 8/21/2012 | 8/21/2012 | P | FAIL |
Mike Jordan
|
|
|
###-#### Jeremy PM Please. Rremove all thumbturns, provide single action door levers, install all missing handrails, move vertical grabbars in ADA stalls to comply with the 39 to 41 inches from wall, provide boots under sinks. Provide final letter from special inspection agency.
|
GCB-Framing | 8/2/2012 | 8/3/2012 | 8/3/2012 | A | PASS |
Mike Jordan
|
|
|
###-#### Drywall inspection. screw pattern for 1hr. fire wall ok.
|
GCB-Framing | 7/24/2012 | 7/25/2012 | 7/25/2012 | A | PASS |
Mike Jordan
|
|
|
###-####. Ok to cover 1hr. wall. Interior steel stud wall for hall to restrooms ok, restroom framing ok, framing at main entry and ticket booth ok.
|
GCB-Framing | 7/19/2012 | 7/20/2012 | 7/20/2012 | A | NR |
Tony Young
|
|
|
Jeremy @ ###-#### Call in advance - AM inspection,, not ready,, walk through conf. only,,, need trades signed off 1st,,, can cover some exterior walls if no trades
|
GCB-Energy | 6/28/2012 | 6/29/2012 | 6/29/2012 | A | PASS |
Jim Sly
|
|
|
Jeremy @ ###-#### Inspection requested for AM. Insulation inspection.
|
GCB-Framing | 6/25/2012 | 6/26/2012 | 6/26/2012 | A | PASS |
Dave Hannah
|
|
|
Jeremy @ ###-#### Call to coordinate ok to insulate dressing rooms and area above and around dressing rooms
|
Plan assigned to (SRZ) | 4/24/2012 | 4/24/2012 | 6/5/2012 | | DONE |
Sam Zahorka
|
|
|
Plan modification 1st review completed. Corrections are needed.
|
Routing Off Site - STRUCTURAL | 5/30/2012 | | 6/5/2012 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 5/31/2012 | | 6/5/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 6/5/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 5/31/2012 | | 5/31/2012 | | PEND |
Sam Zahorka
|
|
|
Pending Structural Review to PASS.
|
Telephone call | | | 5/30/2012 | | DONE |
Christina Prado
|
|
|
Called action couriers for pick up
|
Plan resubmittals received | | | 5/29/2012 | | |
Barbara Stitt
|
|
|
|
Routing Off Site - STRUCTURAL | 5/7/2012 | | 5/17/2012 | | FAIL |
Sam Zahorka
|
|
|
Corrections needed.
|
Meeting | | | 5/14/2012 | | DONE |
Sam Zahorka
|
|
|
Meeting with the applicant, the architect, building official, fire marshal, and building plan reviewer. Discussed previous alternate code approvals, storage commodities, possible occupancy changes per the plan modifications, and building plan review corrections. Requested letter of proposed events, explanation of the concession/bar area, and an updated ratio calculation if need be based on proposed uses. Waiting for corrections from the architect prior to permit issuance.
|
Meeting | | | 5/10/2012 | | DONE |
Sam Zahorka
|
|
|
Scheduled meeting with the architect, building official, fire marshal, applicant, and myself to review project corrections and previous approvals. Meeting is scheduled for Monday, May 14th, at 2:30.
|
Routing - PLAN CHECK | 4/24/2012 | | 5/10/2012 | | FAIL |
Sam Zahorka
|
|
|
Sam Zahorka
|
Plan resubmittals received | | | 4/24/2012 | | DONE |
Barbara Stitt
|
|
|
Plan Modification
|
Plan assigned to (SRZ) | 3/3/2010 | 3/3/2010 | 4/8/2010 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2010 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 4/8/2010 | | DONE |
|
|
|
|
Telephone call | | | 4/8/2010 | | DONE |
|
|
|
called dave hannah to pick up plans and take to garden city
|
Routing - PLAN CHECK | 3/29/2010 | | 4/5/2010 | | PASS |
Sam Zahorka
|
|
|
Pending resubmittals to be inserted into plans. SRZ
4/8/2010 - Received plans from Garden City. Inserted new sheets, approved plans, and sent to Garden City.
|
Routing Off Site - STRUCTURAL | 3/30/2010 | | 4/5/2010 | | PASS |
Sam Zahorka
|
|
|
Recieved structural review resubmittals with corrections. Routed to Structural review.
|
Case Summary (GCB) | | | 4/5/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/2/2010 | | DONE |
|
|
|
|
Telephone call | | | 3/30/2010 | | DONE |
|
|
|
called Action Courier at ###-#### - to pick up plans and take to AHJ Engineering for review
|
Plan resubmittals received | | | 3/29/2010 | | DONE |
Sam Zahorka
|
|
|
|
Telephone call | | | 3/29/2010 | | DONE |
|
|
|
called dave hannah to pick up plans (resubmittals) from garden city
|
Routing Off Site - STRUCTURAL | 3/8/2010 | | 3/22/2010 | | FAIL |
Sam Zahorka
|
|
|
Recieved Structural Review Comments/Corrections. Emailed to the Architect. Waiting for resubmittals with corrections.
|
Telephone call | | | 3/18/2010 | | DONE |
|
|
|
called dave hannah to pick up plans and take to garden city
|
1st review completed | | | 3/17/2010 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/4/2010 | | 3/17/2010 | | FAIL |
Sam Zahorka
|
|
|
|
Case Summary (GCB) | | | 3/15/2010 | | DONE |
Sam Zahorka
|
|
|
|
CHANGE STATUS TO (REV) | | | 3/3/2010 | | DONE |
|
|
|
issued automatically
|
Application received | | | 2/4/2010 | | DONE |
|
|
|
|