Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberGCB10-00003
StatusFinaled
Name REVOLUTION LLC
Site Address 4983 N Glenwood
Project NameBLD2010-00003
Customer Number 
ePlanReview 
Description
(REVOLUTIONS LLC.) **4-24-2012 PLAN MODIFICATION TO INCLUDE: COMPLETELY REVISE THE INTERIOR LAYOUT OF THIS SPACE PER PLANS; RELOCATE THE PROPOSED MEZZANINE; CREATE MORE STORAGE/STAGING AREA WHICH REDUCES THE DESIGN OCCUPANT LOAD; MODIFY THE MEANS OF EGRESS SYSTEM PER PLANS; AND ALL OTHER WORK PER THE APPROVED PLAN, ATTAHCED PLAN REVIEW REPORT, AND ALL OTHER REVIEWING AGFENCIES APPROVALS. SRZ** "Formally the Corridor at Glenwood - NAC Events Center" To convert a 28,195 square foot portion of an existing building to an Event Center per the approved plans. This building was previously reviewed under BLD2009-00073 to renovate and prepare this building for future Tenant Improvements. The work is to include: Provide restrooms accessible to the disabled; provide metal stud framing and insulation to the interior side of the exterior concrete walls from the top of the floor slab to the underside of the roof insulation; construct work counters for future concession sales; construct non-bearing interior wall partitions for the restrooms and dressing room; modify and provide openings in the existing walls for new egress doors; construct a new 2,127 square foot mezzanine; installation of suspended ceiling system and related lighting; installation of new mechanical system units; and interior finishes in compliance with chapter 8 of the 2006 IBC. All work per the approved plans, attached plan review report, Engineering, and all other reviewing agencies approvals. NOTE: This building is fully fire sprinklered for area increase. All alterations and modifications to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department. **SRZ** PWU2010-00008
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final8/21/20128/22/20128/22/2012APASS
DetailsMike Jordan
Jeremy @ ###-####
As early in the morning as possible please. Ok for perm occ. All issues have been resolved.
GCB-Final8/20/20128/21/20128/21/2012PFAIL
DetailsMike Jordan
###-#### Jeremy
PM Please. Rremove all thumbturns, provide single action door levers, install all missing handrails, move vertical grabbars in ADA stalls to comply with the 39 to 41 inches from wall, provide boots under sinks. Provide final letter from special inspection agency.
GCB-Framing8/2/20128/3/20128/3/2012APASS
DetailsMike Jordan
###-####
Drywall inspection. screw pattern for 1hr. fire wall ok.
GCB-Framing7/24/20127/25/20127/25/2012APASS
DetailsMike Jordan
###-####. Ok to cover 1hr. wall. Interior steel stud wall for hall to restrooms ok, restroom framing ok, framing at main entry and ticket booth ok.
GCB-Framing7/19/20127/20/20127/20/2012ANR
DetailsTony Young
Jeremy @ ###-####
Call in advance - AM inspection,, not ready,, walk through conf. only,,, need trades signed off 1st,,, can cover some exterior walls if no trades
GCB-Energy6/28/20126/29/20126/29/2012APASS
DetailsJim Sly
Jeremy @ ###-####
Inspection requested for AM.
Insulation inspection.
GCB-Framing6/25/20126/26/20126/26/2012APASS
DetailsDave Hannah
Jeremy @ ###-####
Call to coordinate ok to insulate dressing rooms and area above and around dressing rooms
Plan assigned to (SRZ)4/24/20124/24/20126/5/2012 DONE
DetailsSam Zahorka
Plan modification 1st review completed. Corrections are needed.
Routing Off Site - STRUCTURAL5/30/2012 6/5/2012 PASS
DetailsSam Zahorka
Routing - PLAN CHECK5/31/2012 6/5/2012 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  6/5/2012 DONE
DetailsSam Zahorka
Issue and Courier  6/5/2012 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK5/31/2012 5/31/2012 PEND
DetailsSam Zahorka
Pending Structural Review to PASS.
Telephone call  5/30/2012 DONE
DetailsChristina Prado
Called action couriers for pick up
Plan resubmittals received  5/29/2012  
DetailsBarbara Stitt
Routing Off Site - STRUCTURAL5/7/2012 5/17/2012 FAIL
DetailsSam Zahorka
Corrections needed.
Meeting  5/14/2012 DONE
DetailsSam Zahorka
Meeting with the applicant, the architect, building official, fire marshal, and building plan reviewer. Discussed previous alternate code approvals, storage commodities, possible occupancy changes per the plan modifications, and building plan review corrections. Requested letter of proposed events, explanation of the concession/bar area, and an updated ratio calculation if need be based on proposed uses. Waiting for corrections from the architect prior to permit issuance.
Meeting  5/10/2012 DONE
DetailsSam Zahorka
Scheduled meeting with the architect, building official, fire marshal, applicant, and myself to review project corrections and previous approvals. Meeting is scheduled for Monday, May 14th, at 2:30.
Routing - PLAN CHECK4/24/2012 5/10/2012 FAIL
DetailsSam Zahorka
Sam Zahorka
Plan resubmittals received  4/24/2012 DONE
DetailsBarbara Stitt
Plan Modification
Plan assigned to (SRZ)3/3/20103/3/20104/8/2010 DONE
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  4/8/2010 DONE
DetailsSam Zahorka
Issue and Courier  4/8/2010 DONE
Details
Telephone call  4/8/2010 DONE
called dave hannah to pick up plans and take to garden city
Routing - PLAN CHECK3/29/2010 4/5/2010 PASS
DetailsSam Zahorka
Pending resubmittals to be inserted into plans. SRZ
4/8/2010 - Received plans from Garden City. Inserted new sheets, approved plans, and sent to Garden City.
Routing Off Site - STRUCTURAL3/30/2010 4/5/2010 PASS
DetailsSam Zahorka
Recieved structural review resubmittals with corrections. Routed to Structural review.
Case Summary (GCB)  4/5/2010 DONE
Plan resubmittals received  4/2/2010 DONE
Telephone call  3/30/2010 DONE
called Action Courier at ###-#### - to pick up plans and take to AHJ Engineering for review
Plan resubmittals received  3/29/2010 DONE
DetailsSam Zahorka
Telephone call  3/29/2010 DONE
called dave hannah to pick up plans (resubmittals) from garden city
Routing Off Site - STRUCTURAL3/8/2010 3/22/2010 FAIL
DetailsSam Zahorka
Recieved Structural Review Comments/Corrections. Emailed to the Architect. Waiting for resubmittals with corrections.
Telephone call  3/18/2010 DONE
Details
called dave hannah to pick up plans and take to garden city
1st review completed  3/17/2010 FAIL
DetailsSam Zahorka
Routing - PLAN CHECK3/4/2010 3/17/2010 FAIL
DetailsSam Zahorka
Case Summary (GCB)  3/15/2010 DONE
DetailsSam Zahorka
CHANGE STATUS TO (REV)  3/3/2010 DONE
issued automatically
Application received  2/4/2010 DONE