Permit Information
Permit NumberGCB10-00009
StatusFinaled
Name Hayden Homes
Site Address 10303 W LAKELAND
Project NameBLD2010-00009
Customer Number 
ePlanReview 
Description
To construct a 1,408 square foot, One story, three bedroom, two bath, Single family dwelling with a 403 square foot attached garage and a 24 square foot covered front porch. "THE PERMIT HOLDER is responsible to comply with R602 of the 2006 International Residential Code." 1-hour fire-resistance construction is required on all projections closer than 5 feet to the property line. Distance to property line for fire rated construction is measured from the finished exterior of the exterior wall. Any walls less than 5' from the property line are required to have 1-hour fire-resistance construction. This lot is located in the Flood plain. All work per the approved plans, the attached plan review report, and All other reviewing agencies approvals. SRZ
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final7/12/20107/13/20107/13/2010APASS
DetailsMike Jordan
Scope: Final (Signature Only)Contact: Rich @ ###-####. Final ok.
GCB-Final7/7/20107/8/20107/8/2010ANR
DetailsMike Jordan
Scope: FinalContact: Rich @ ###-####. Cards not signed, mech inspection failed. Needs to have cards signed to verify all finals are completed. Trades permits are not all attached and cannot verify finals on all trades. Spoke to leon with Garden City, they have been only looking at structural sign off. Noted to leon that card needs to have required final sign offs before issueing certificate of occupancies because trades permits are not all attached to building permits. Called contractor to have him reschedule all of his finals to have card signed. Also spoke to Bob Archibald about above issue.
GCB-Energy5/10/20105/10/20105/10/2010APASS
DetailsDave Hannah
GCB-Framing5/7/20105/10/20105/10/2010APASS
DetailsDave Hannah
Scope of inspection: Wall installationContact: Rich @ ###-####
GCB-Framing5/6/20105/7/20105/7/2010APASS
DetailsDave Hannah
Scope of inspection: Framing / Rough in
Contact: Rich @ ###-#### ok to insulate
GCB-Energy5/6/20105/7/20105/7/2010APART
DetailsDave Hannah
Scope of inspection: EnergyContact: Rick @ ###-#### seal pakage ok
GCB-Footing4/6/20104/7/20104/7/2010APASS
DetailsDave Hannah
9:30 am requested
Plan assigned to (SRZ)3/10/20103/10/20103/17/2010 DONE
DetailsSam Zahorka
Routing - PLAN CHECK3/10/2010 3/17/2010 PASS
DetailsSam Zahorka
1st review completed  3/17/2010 DONE
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  3/17/2010 DONE
DetailsSam Zahorka
Telephone call  3/17/2010 DONE
DetailsSam Zahorka
Called the applicant and explained the requirement for eve and possibly wall protection due to fire separation distance less than five feet. SRZ
Issue and Courier  3/17/2010 DONE
Details
Application received  3/2/2010 DONE