GCB-Final | 7/29/2010 | 8/2/2010 | 8/2/2010 | A | PASS |
Dave Hannah
|
|
|
Scope: FinalContact: Bob @ ###-####
|
GCB-Framing | 5/13/2010 | 5/14/2010 | 5/14/2010 | A | PASS |
Dave Hannah
|
|
|
Scope of inspection: Framing re-inspectionConatact: Bob @ ###-#### ok to cover work is per revised engineering
|
GCB-Framing | 5/12/2010 | 5/13/2010 | 5/13/2010 | A | PART |
Dave Hannah
|
|
|
Scope of inspection: FramingContact: Bob @ ###-####CUSTOMER HAS REQUESTED A.M. INSPECTION PLEASE ok to cover int walls but need engineer to ok post and beam on ext wall correction notice on site
|
Plan assigned to (SRZ) | 3/18/2010 | 3/18/2010 | 3/26/2010 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/18/2010 | | 3/26/2010 | | PASS |
Sam Zahorka
|
|
|
Pending call back from engineer to verify footing size for new beam.
|
Plan resubmittals received | | | 3/26/2010 | | DONE |
Sam Zahorka
|
|
|
Engineering calculations recieved by email for the new beam, column, and Foundation design.
|
Issue and Courier | | | 3/26/2010 | | DONE |
|
|
|
|
Telephone call | | | 3/26/2010 | | DONE |
|
|
|
called dave hannah to pick up permit and take to garden city
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2010 | | DONE |
Sam Zahorka
|
|
|
|
Telephone call | | | 3/23/2010 | | DONE |
Sam Zahorka
|
|
|
Spoke with Chip Gallagher about needing engineering calculation for the new footing design. He stated he would contact the engineer and have him call me directly.
|
1st review completed | | | 3/22/2010 | | DONE |
Sam Zahorka
|
|
|
|
Application received | | | 3/11/2010 | | DONE |
|
|
|
|