Permit Information
Permit NumberGCB10-00011
StatusFinaled
Name Visser Building Co.LC
Site Address 4776 RIVERINE
Project NameBLD2010-00010
Customer Number 
ePlanReview 
Description
To construct an interior remodel to an existing One story, Single family dwelling to include: construct interior non-bearing walls to reconfigure the Utility/Laundry room areas; construct interior non-bearing walls to reconfigure the Master bathroom and Master closet areas; Remove an existing bearing wall between the kitchen and dining room and replace with a new beam to carry the existing roof; raise the existing floor in the living room to match the entry and dining room floor heights; remove and relocate select existing doors and windows; add new windows in new and existing openings; and all other work per approved plans, all red-lining, and plan review report. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final7/29/20108/2/20108/2/2010APASS
DetailsDave Hannah
Scope: FinalContact: Bob @ ###-####
GCB-Framing5/13/20105/14/20105/14/2010APASS
DetailsDave Hannah
Scope of inspection: Framing re-inspectionConatact: Bob @ ###-#### ok to cover work is per revised engineering
GCB-Framing5/12/20105/13/20105/13/2010APART
DetailsDave Hannah
Scope of inspection: FramingContact: Bob @ ###-####CUSTOMER HAS REQUESTED A.M. INSPECTION PLEASE ok to cover int walls but need engineer to ok post and beam on ext wall correction notice on site
Plan assigned to (SRZ)3/18/20103/18/20103/26/2010 DONE
DetailsSam Zahorka
Routing - PLAN CHECK3/18/2010 3/26/2010 PASS
DetailsSam Zahorka
Pending call back from engineer to verify footing size for new beam.
Plan resubmittals received  3/26/2010 DONE
DetailsSam Zahorka
Engineering calculations recieved by email for the new beam, column, and Foundation design.
Issue and Courier  3/26/2010 DONE
Details
Telephone call  3/26/2010 DONE
called dave hannah to pick up permit and take to garden city
PLANS/APPL TAKEN TO FRONT DESK  3/26/2010 DONE
DetailsSam Zahorka
Telephone call  3/23/2010 DONE
DetailsSam Zahorka
Spoke with Chip Gallagher about needing engineering calculation for the new footing design. He stated he would contact the engineer and have him call me directly.
1st review completed  3/22/2010 DONE
DetailsSam Zahorka
Application received  3/11/2010 DONE