GCB-Final | 9/13/2010 | 9/14/2010 | 9/14/2010 | A | PASS |
Dave Hannah
|
|
|
Scope: FinalContact: Bart @ ###-####Call for access please
|
GCB-Framing | 7/12/2010 | 7/13/2010 | 7/13/2010 | A | PASS |
Mike Jordan
|
|
|
Scope: FramingContact: Curtis @ ###-####** Call 30 Mins in Advance**
|
GCB-Footing | 5/7/2010 | 5/10/2010 | 5/10/2010 | A | PASS |
Dave Hannah
|
|
|
Scope of inspection: FootingContact: Bart @ ###-####
|
Plan assigned to (SRZ) | 4/20/2010 | 4/20/2010 | 5/6/2010 | | DONE |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 5/6/2010 | | |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 5/6/2010 | | 5/6/2010 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/6/2010 | | DONE |
Sam Zahorka
|
|
|
|
Case Summary (GCB) | | | 5/6/2010 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 5/6/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/20/2010 | | 4/21/2010 | | FAIL |
Sam Zahorka
|
|
|
|
1st review completed | | | 4/21/2010 | | FAIL |
Sam Zahorka
|
|
|
Beam calculations have been requested from Zac Shear w/ Boise Cascade. Connections also needed and have been requested. SRZ
|
Telephone call | | | 4/21/2010 | | DONE |
Sam Zahorka
|
|
|
Beam calculations have been requested from Zac Shear w/ Boise Cascade. Connections also needed and have been requested. SRZ
|
Plan resubmittals requested | | | 4/21/2010 | | DONE |
Sam Zahorka
|
|
|
Beam calculations have been requested from Zac Shear w/ Boise Cascade. Connections also needed and have been requested. SRZ
|
Application received | | 4/20/2010 | | | |
|
|
|
|