GCB-Final | 9/30/2010 | 10/1/2010 | 10/1/2010 | A | PASS |
Dave Hannah
|
|
|
Scope: FinalContact: Walt @ ###-####
|
Case Summary (GCB) | | | 9/30/2010 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 9/29/2010 | | DONE |
|
|
|
plan mod received
|
Meeting | | | 9/22/2010 | | DONE |
Sam Zahorka
|
|
|
Meeting at the building site with the applicant, the architect, the Fire reviewer, and myself to go over corrections needed for the plan modification resubmittals. Explained all changes from the approved plans need to be detailed on the plan modification submittals. Also suggested they obtain a mechanical permit along with the required inspections. All plan modification items are IFC changes - (Spill control and secondary containment design).
|
Plan assigned to (SRZ) | 5/28/2010 | 5/28/2010 | 7/6/2010 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 6/29/2010 | | 7/6/2010 | | PASS |
Sam Zahorka
|
|
|
Permit issuance pending Mechanical Review to pass. Contact Lee Rice.
|
Routing - PLAN CHECK | 7/6/2010 | | 7/6/2010 | | PASS |
Troy James
|
|
|
Route to Mechanical review per Lee Rice.
|
Case Summary (GCB) | | | 7/6/2010 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/6/2010 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 7/6/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/29/2010 | | DONE |
|
|
|
3 sets rec'd
|
Meeting | | | 6/22/2010 | | DONE |
Sam Zahorka
|
|
|
Meeting here at Boise city with the applicant, the architect, the Fire reviewer, and myself to go over corrections and resubmittals.
Re-submittals with all corrections made (including mechanical plans) were promised to be resubmitted by 6/25/10 so the permit could be issued for the applicant. Resubmittals were not recieved until 6/29/10.
|
Plan resubmittals requested | | | 6/14/2010 | | DONE |
Sam Zahorka
|
|
|
|
Telephone call | | | 6/14/2010 | | DONE |
Sam Zahorka
|
|
|
Telephone conversation with Walt Kerpa the applicant. Explained the 1st review is complete and Garden City should be sending it to him and the Architect this afternoon. I suggested he schedule a meeting with Garden City for this Wednesday morning to discuss Plan Review Corrections.
|
Telephone call | | | 6/14/2010 | | DONE |
Sam Zahorka
|
|
|
Left message with the Architect to contact me to go over plan review corrections.
|
Routing - PLAN CHECK | 5/28/2010 | | 6/11/2010 | | FAIL |
Sam Zahorka
|
|
|
Plan Review corrections Required.
|
Case Summary (GCB) | | | 6/11/2010 | | DONE |
Sam Zahorka
|
|
|
|
1st review completed | | | 6/11/2010 | | DONE |
Sam Zahorka
|
|
|
Failed 2006 IBC Plan Check. SRZ
|
Application received | | | 5/24/2010 | | DONE |
Barbara Stitt
|
|
|
|