GCB-Final | 4/13/2011 | 4/14/2011 | 4/14/2011 | A | PASS |
Dave Hannah
|
|
|
FinalMitch @ ###-####PM Inspection
|
GCB-Ceiling Grid | 3/30/2011 | 3/31/2011 | 3/31/2011 | A | PASS |
Mike Jordan
|
|
|
Ceiling GridMitch @ ###-####Call in advance please. Ceiling grid ok to cover.
|
GCB-Ceiling Grid | 3/24/2011 | 3/25/2011 | 3/25/2011 | A | NR |
Mike Jordan
|
|
|
Ceiling GridMitch @ ###-####Call in advance please - AM Inspection. Neesd to install remainder of clips and provide wires for diffusers.
|
GCB-Energy | 1/13/2011 | 1/14/2011 | 1/14/2011 | A | PART |
Mike Jordan
|
|
|
Scope: EnergyContact: Mitch @ ###-####. Plan review notes were provided. Needs to show provided windows with U-factor of .99 will meet the prescriptive method of the IECC, max u-factor should have been .45. Ok to cover.
|
GCB-Framing | 1/11/2011 | 1/12/2011 | 1/12/2011 | A | CANC |
Mike Jordan
|
|
|
Scope: Framing Contact: Mitch @ ###-#### PM Inspection Please. Inspection was done in the PM.
|
GCB-Framing | 1/12/2011 | 1/12/2011 | 1/12/2011 | P | PART |
Mike Jordan
|
|
|
Interior wood framed walls and furouts only. Needs to install all backing for ada elements in restroom and provide plan review notes. ok to insulate.
|
Plan assigned to (SRZ) | 7/23/2010 | 7/23/2010 | 10/18/2010 | | DONE |
Sam Zahorka
|
|
|
Failed 2nd Review - 10/8/10
|
Routing - PLAN CHECK | 10/18/2010 | | 10/18/2010 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2010 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 10/18/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/15/2010 | | DONE |
|
|
|
|
Case Summary (GCB) | | | 10/8/2010 | | DONE |
Sam Zahorka
|
|
|
|
Plan resubmittals requested | | | 10/8/2010 | | DONE |
Sam Zahorka
|
|
|
See plan review report dated 10-7-10
|
Routing - PLAN CHECK | 9/30/2010 | | 10/8/2010 | | FAIL |
Sam Zahorka
|
|
|
Resubmittals requested.
|
Plan resubmittals received | | | 9/30/2010 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 8/30/2010 | | DONE |
Sam Zahorka
|
|
|
Initial review letter sent. Resubmittals have been requested.
|
Telephone call | | | 8/30/2010 | | DONE |
Sam Zahorka
|
|
|
I spoke with the architect George McLean about the intital plan review letter I sent. We concluded until we get the occupancy classification clarified a plan review could not be completed. I also suggested he call me prior to resubmitting that way we could identify any other major items defined by our occupancy classification answer. SRZ
|
Routing - PLAN CHECK | 7/23/2010 | | 8/26/2010 | | FAIL |
Sam Zahorka
|
|
|
Flammable liquid storage amounts need to be clarified prior to completeing the 1st review.
|
1st review completed | | | 8/26/2010 | | FAIL |
Sam Zahorka
|
|
|
|
Telephone call | | | 8/26/2010 | | DONE |
Sam Zahorka
|
|
|
Spoke with Ron Amandus with the Fire Department. Discussed his review and need the applicant to submit a storage rack layout, identify the aisles, and identify the amount of storage.
|
Telephone call | | | 8/26/2010 | | DONE |
Sam Zahorka
|
|
|
I spoke with the Architect George Mclean about the occupancy classification of this tenant. He stated he originaly evaluated this building as a mixed occupancy S-1 and M. The submitted plans show this. He shared that the applicant, owner, the fire inspector/reviewer, Matt the Fire Sprinkler guy, and himself all met at Garden City hall and communicated this tenant to be a Hazardous Occupancy (H-3 or H-2). He stated the materials (type of liquid), Class, amounts, and locations of the anticipated contents will not be provided until the owner is ready to occupy the building. I then explained to Mr. Mclean the permit issuance is pending this information. he requested a letter to explain what is needed so he could give it to his clients.
|
Application received | | | 6/28/2010 | | DONE |
|
|
|
|