GCB-Final | 3/11/2011 | 3/14/2011 | 3/14/2011 | A | PASS |
Mike Jordan
|
|
|
FinalRyan @ ###-####PM Inspection - Call in advance please. All poutstanding issues have been repaired. Structural final ok.
|
GCB-Final | 3/11/2011 | 3/11/2011 | 3/11/2011 | A | FAIL |
Mike Jordan
|
|
|
FinalRyan @ ###-####. Provide lock indicator on main enterance/exit door, remove key lock hardware on rear door, raise handrail to mezz. Correction notice was issued.
|
GCB-Courtesy | 2/25/2011 | 2/28/2011 | 2/28/2011 | A | DONE |
Mike Jordan
|
|
|
Courtesy (Conference)Ryan @ ###-####Call in advance please. Spoke to cintractor bout sidewalk slope at ada crossing.
|
GCB-Energy | 1/28/2011 | 1/31/2011 | 1/31/2011 | A | PASS |
Mike Jordan
|
|
|
Scope: EnergyContact: Ryan @ ###-#### Insulation ok. Also verifed installation of truss bracing that was noted missing during framing inspection.
|
GCB-Framing | 1/25/2011 | 1/26/2011 | 1/26/2011 | A | PASS |
Tony Young
|
|
|
Scope: FramingContact: Ryan @ ###-#### NOTE verify truss braces at energy code inspection
|
GCB-Framing | 1/13/2011 | 1/13/2011 | 1/13/2011 | P | PART |
Mike Jordan
|
|
|
Shear nailing-Ryan Phone #: ###-####. Exterior shear nailing only. ok.
|
GCB-Shearwall | 1/4/2011 | 1/5/2011 | 1/5/2011 | A | PART |
Dave Hannah
|
|
|
Scope: ShearwallContact: Ryan @ ###-#### clips on rim to top plate ok to cover
|
GCB-Fndatn/slab ins/fld vent | 12/16/2010 | 12/17/2010 | 12/17/2010 | A | PART |
Dave Hannah
|
|
|
Scope: Foundation/Slab Insulation/EtcContact: Ryan @ ###-#### ok to pour lid
|
GCB-Fndatn/slab ins/fld vent | 12/3/2010 | 12/6/2010 | 12/6/2010 | A | PART |
Mike Jordan
|
|
|
Scope: FoundationContact: Ryan @ ###-####. Vertical and horizontal reinforcement for perimeter walls. Will have special inspection
|
GCB-Footing | 11/19/2010 | 11/22/2010 | 11/22/2010 | A | PART |
Mike Jordan
|
|
|
Scope: FootingsContact: Ryan @ ###-####. REbar for matslab and verts for wall. Work in progress, will have special inspection.
|
Plan assigned to (SRZ) | 9/17/2010 | 9/17/2010 | 10/21/2010 | | DONE |
Sam Zahorka
|
|
|
Failed Plumbing Review 10-13-10
**Additional PLUMBING PLAN REVIEW TIME**
|
Routing - PLAN CHECK | 10/21/2010 | | 10/21/2010 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/21/2010 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 10/21/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/13/2010 | | 10/20/2010 | | PEND |
Sam Zahorka
|
|
|
Pending Plumbing to pass
|
Plan resubmittals received | | | 10/20/2010 | | DONE |
|
|
|
|
Miscellaneous Hourly | | | 10/20/2010 | | PASS |
Bill VanDegrift
|
|
|
Plumbing Resubmittal corrections Routed to Bill Vandegrift. resubmitted plans dater 10/20/10. UPC710. duplex sump pumps, 3" min. discharge. or approved grinders.
|
Plan resubmittals requested | | | 10/19/2010 | | DONE |
Sam Zahorka
|
|
|
Project failed plumbing review. Corrections requested per Bill Vandergrift.
|
Plan resubmittals received | | | 10/13/2010 | | DONE |
Sam Zahorka
|
|
|
Recieved Statement of Special Inspection. Plan issuance pending Plumbing approval.
|
Telephone call | | | 10/11/2010 | | DONE |
Sam Zahorka
|
|
|
Left message with Glenn Walker. Need the Statement of Special Inspection form #310 prior to issuance.
|
Miscellaneous Hourly | | | 10/11/2010 | | FAIL |
Bill VanDegrift
|
|
|
Routed to Plumbing Cold water to hose bibs in the shop area must be protected by an R.P. installed over the floor sink. 12.56" min. vent through the roof. buplex sump pumps min. 3" discharge required. remove the floor drain in the basement restroom and raise the foor sink 1" min. for pretreatment requirements.
|
Telephone call | | | 10/6/2010 | | DONE |
Sam Zahorka
|
|
|
Spoke with Glen Walker the architect. Requested application #310 be filled out by the Engineer and emailed back to me prior to issuance.
|
Routing - PLAN CHECK | 9/17/2010 | | 10/5/2010 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 10/5/2010 | | DONE |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 9/21/2010 | | DONE |
Sam Zahorka
|
|
|
Received structural calculations.
|
Application received | | 9/17/2010 | 9/17/2010 | | DONE |
Barbara Stitt
|
|
|
|
GCB-Final | 3/10/2011 | 3/11/2011 | | A | |
|
|
|
FinalRyan @ ###-####
|