GCB-Final | 3/31/2011 | 4/1/2011 | 4/1/2011 | A | PASS |
Mike Jordan
|
|
|
FinalRich @ ###-####. Structural final ok.
|
GCB-Energy | 12/28/2010 | 12/29/2010 | 12/29/2010 | A | PASS |
Mike Jordan
|
|
|
Scope: EnergyContact: Rich @ ###-####
|
GCB-Framing | 12/27/2010 | 12/28/2010 | 12/28/2010 | A | PASS |
Dave Hannah
|
|
|
Scope: FramingContact: Rich @ ###-####
|
GCB-Fndatn/slab ins/fld vent | 11/15/2010 | 11/16/2010 | 11/16/2010 | A | PASS |
Dave Hannah
|
|
|
Scope: FoundationContact: Bill @ ###-####
|
GCB-Footing | 11/12/2010 | 11/15/2010 | 11/15/2010 | A | PASS |
Dave Hannah
|
|
|
Scope: FootingsContact: Bill @ ###-####
|
Plan assigned to (SRZ) | 10/15/2010 | 10/15/2010 | 10/20/2010 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2010 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 10/20/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/15/2010 | | 10/19/2010 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 10/19/2010 | | DONE |
Sam Zahorka
|
|
|
|
Application received | | | 10/13/2010 | | DONE |
|
|
|
|